5MWp Power Station, 2017


 

Client: Jordan University for Science and Technology

Status: Grid connected in February 2017

DNO:    Irbid Distribution and Electricity Company (IDECO)

Description: The projects was awarded based on competitive tender to the JV of Mustakbal, Masannat Engineering and Construction Co., and Enerparc.  The scope was to design and build the PV plant within a contract period of one year as a net-metering project on the campus of JUST.

Included in the scope was the grid impact study, third party engineering validation, and third party testing and commissioning which was done by TUV.  The system comprised of Jinko 265W polycrystalline modules, German fixed tilt mounting structure, SMA string inverters, MV transformers and switching stations in accordance with IDECO’s requirements.  The plant is monitored using a Skytron system, as well as a CCTV system.

The project received a TUV certificate for compliance with EN 62446:2009.

Mustakbal is also responsible for operating and maintaining the power plant for four years after commissioning.


5MWp Power Station / Wheeling


 

Client: Kempinski Dead Sea

Status: Grid connection planned for May 2017, 30% complete

DNO: Electricity Distribution Company (EDCO)

Description: The project was awarded based on competitive tender to the JV of Mustakbal, Masannat Engineering and Construction Co., and Enerparc.  The scope was to design and build the PV plant within a contract period of seven months in Judaydeh, Karak under a wheeling scheme.

Included in the scope is engineering, procurement, construction and operation and maintenance for two years.   The system comprised of Jinko polycrystalline modules, Nextracker single axis tracking mounting structure, SMA string inverters, MV transformers and switching stations in accordance with EDCO’s requirements.  The plant is monitored using a Gantner system, as well as a CCTV and parameter detection system.


2MWp Wheeling Project

 

Client: Khalidi Medical

Status: Grid connection planned for May 2017, 80% complete

DNO: Jordan Electricity Distribution Co. (JEPCO)

Description: Mustakbal clean tech is implementing the project in cooperation with Masannat (as subcontractor) and Enerparc as technical support.   The scope was to design and build the PV plant within a contract period of six months in the Jizeh area (40 km South of Amman) under a wheeling scheme.

Included in the scope is engineering, procurement, construction and operation and maintenance for two years.   The system comprised of Jinko polycrystalline modules, Nextracker single axis tracking mounting structure, SMA string inverters, MV transformers and switching stations in accordance with JEPCO’s requirements.  The plant is monitored using a Gantner system, as well as a CCTV and parameter detection system.


750kWp Wheeling Project


 

Client: King Hussein Foundation

Status: Grid connected in Jan 2017

DNO: Jordan Electricity Distribution Co. (JEPCO)

Description: Mustakbal clean tech engineered and installed this 750kWp wheeling project in Shafa Badran. It supports over twenty electricity consumers belonging to the KHF family, including Tamweelcom.  The equipment is based on Jinko polycrystalline modules, German origin mounting structure, and SMA inverters.  JEPCO supplied and installed the MV substation.  Mustakbal is responsible for operating and maintaining the plant for three years. NERC participated as a third party engineering consultant together with KHF engineering team.


2MWp PV Plant in Azrak Refugee Camp


 

Client: UNHCR

Status: To be connected in April 2017

DNO: EDCO

Description: Mustakbal clean tech engineered and installed this 2MWp netmetering project that is funded by IKEA for the UNHCR refuge camp in Azrak.  The equipment is based on Jinko polycrystalline modules, German origin mounting structure, SMA inverters, two MV transformers and related switchgear.  TUV will provide the third party commissioning inspection support.